Where the contract between the parties stipulates that variation works shall be carried only with written instructions, and there were no written instructions but only oral instructions, the claim for variations will not be valid: Vim Engineering Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd [2021] SGHC 63. The …
Continue readingTag: Variations
Establishing a Variation Claim
In Comfort Management Pte Ltd v OGSP Engineering Pte Ltd and another (No. 2) [2020] SGHC 165, the High Court approved a two-stage approach to establish a variation claim. First a claimant has to show that a valid instruction has been issued for the variation. The instruction has to be …